Cheap firm clean power becomes available at scale
- Likelihood, two years
- 3Possible
- to end-2028
- Likelihood, ten years
- 4Likely
- to end-2036
- Systemic impact
- 4Major
- global
- National impact
- 4Major
- typical highly exposed nation
- Onset pace
- Months
- Duration (acute phase)
- 5 years
- Warning time
- Months
- Scope
- Global
- Recovery horizon
- Structural
- Capability load
- Hard 2/3Soft 1/3Economic 3/3
- domains loaded High
- Concurrency
- Standalone
- triggers 5 · triggered by 5
- Confidence · movement
- medium
- new
Rated at Standard Severe. Event reach: global event. Source of scores: model-panel-v0.5. Upside scenario: impact levels measure the scale of change, not loss.
03Narrative
Dateline: June 2035
The result that changed investment decisions was published in September 2030. Independent engineers had audited eleven commercial plants in five climate zones over two full years. Each combined solar or wind generation, battery storage and one firm clean source: enhanced geothermal at seven sites, small modular fission at two and long-duration storage at two. All eleven had met a contracted reliability standard of 99.9 per cent of hours at a delivered cost 40 per cent below a new gas or coal plant in the same market. The designs were standard and the audit data were public.
Lenders acted on the finding within months. By early 2032 standardised projects were reaching financial close in 18 months or less from first application, and their cost of debt had fallen below that of new thermal plant. Developers ordered the same module, cell and drilling packages in volume. Orders for transformers, cable and rigs exceeded supply within a year, and prices for lithium, copper and graphite rose sharply before new capacity arrived.
The gain was not distributed by resource. It was distributed by the ability to connect. Nations that had approved transmission corridors, staffed their permitting offices and reformed wholesale markets to pay for firm capacity brought projects into service in three years. Their industrial electricity costs were 30 per cent lower by 2035, and smelters, chemical plants, electrolysers and data centres signed 15-year supply contracts there. Nations with connection queues of five years or more saw the same projects financed and then left waiting. Several curtailed large volumes of midday output while still paying for imported gas in the evening.
Importers of oil and gas recorded lower fuel bills from 2033 as heat, transport and industry electrified faster than planned. Households saw the difference later than industry, because network charges rose to pay for the new lines.
The loss arrived through expectations before it arrived through volumes. Long-term demand forecasts for oil, gas and coal were revised down in 2031 and again in 2032. Reserves were written down, new field developments were cancelled and the borrowing costs of hydrocarbon-dependent states rose while their export receipts were still close to normal. Producers with low costs and large sovereign funds maintained output and used the interval to diversify. Producers without buffers cut capital spending first, then subsidies and public pay. Three had requested external financing programmes by 2034. Utilities holding recently built gas and coal plant sought compensation for early closure, and coal regions lost employment faster than retraining schemes could absorb.
By June 2035 the threshold itself was no longer in dispute. The remaining questions were administrative: how quickly a state could approve a line, train electricians and drillers, secure materials and replace a revenue base.
The dateline is illustrative, not a forecast. The narrative is hypothetical; the historical anchors below are real events.
04Summary
Independent commercial trials establish that a replicable combination of renewables, storage and firm clean generation supplies reliable electricity at 40 per cent below the cost of new fossil plant across several climate zones. Standardised projects reach financial close within 18 months. Early adopters cut industrial electricity costs by 30 per cent within five years, which accelerates electrification and changes where energy-intensive industry and data centres invest. The gain goes to nations that connect projects, secure materials and reform power markets quickly. Hydrocarbon-dependent revenues weaken as expected long-term demand and asset values are revised down, ahead of the fall in volumes.
- Who gains
- Energy importers with grid capacity: much of Europe, Japan, Korea, India and China
- Industrial locations that can connect new plant within three years
- Energy-intensive industry and data centres, through lower and more stable power costs
- Makers of modules, cells, drilling equipment, transformers and cable
- Producers of copper, lithium, graphite and other transition minerals
- Nations with low electricity access, where the cost of reliable supply falls
- Who loses
- Hydrocarbon-dependent states without fiscal buffers or sovereign funds
- Owners of recently built gas and coal plant and of undeveloped reserves
- Coal, oil and gas regions and the workers employed there
- Nations with long connection queues, which lose industry to faster neighbours
- States whose external leverage rested on supplying fuel
A shock most would count as progress. It is not upside for everyone: each record names who gains and who loses. Impact levels measure the scale of change, in either direction, and loads mark the capabilities a nation needs in order to capture the gain or absorb the loss.
05Historical anchors
| Event | Date | What happened | Calibrates |
|---|---|---|---|
| Solar cost decline | 2010–2020 | The cost of electricity from utility-scale solar fell by more than 80 per cent in a decade as manufacturing scaled and designs standardised. | The size of cost reduction that a standard, mass-produced energy technology can deliver in ten years, and the basis for the ten-year likelihood band. |
| Battery storage cost record | 2025 | The benchmark cost of a four-hour battery project fell 27 per cent in a year to US$78 per MWh, the lowest since tracking began in 2009. | Storage is the component that turns variable output into dependable supply. The rate of decline supports a combined system priced below new fossil plant. |
| Enhanced geothermal at Cape Station | 2026 | The first 100 MW phase of the largest enhanced geothermal project was scheduled to deliver power to the grid. | A firm clean source at commercial scale exists but has no long operating record. The scenario's trials supply the record that lenders require. |
| Pakistan solar import surge | 2024 | Pakistan imported about 17 GW of solar modules in 2024, according to Ember's analysis of Chinese export data, as households and firms responded to high grid tariffs. Grid electricity sales fell and the finances of the distribution companies weakened. | Onset in months: adoption can outrun planning once a price threshold is crossed, and the incumbent system's revenue weakens before its assets are retired. |
| US grid interconnection queue | End of 2023 | About 2,600 GW of generation and storage capacity was waiting in US interconnection queues at the end of 2023, more than twice the installed fleet, according to Lawrence Berkeley National Laboratory. Projects completed in 2023 had typically taken about five years from request to operation. | Connection and permitting, not cost, set the pace of delivery. A nation with a five-year queue captures little of the gain inside the five-year test period. |
| Oil price collapse | 1986 | Oil prices fell by more than half within months. Exporter revenues fell with them, which strained Soviet finances and forced spending cuts across producer states. | The upper bound of the loss for hydrocarbon-dependent states. In this scenario the revision is to expected demand, so the loss arrives more slowly than in 1986. |
06Parameters
Shown at their preset values. Parameters are not adjustable in this release and nothing on this page is computed from them. Custom settings run (Phase B) but are labelled 'non-standard run' and excluded from comparisons.
Common variables at Standard Severe · read-only
- 1. Severity
- major
- severe (Standard Severe)
- extreme
- 2. Duration (acute phase)
- 30 days
- 90 days
- 1 year
- 3 years
- 5 years (Standard Severe)
- 3. Onset pace
- days
- weeks
- months (Standard Severe)
- years
- 4. Warning time
- none
- days
- months (Standard Severe)
- 5. Scope
- national
- regional
- global (Standard Severe)
- 6. Origin
- natural
- accidental (Standard Severe)
- adversarial (great power / neighbour / non-state)
- negotiated
Standard Severe: accidental (technological)
- 7. External support
- full
- partial (Standard Severe)
- none
- 8. Concurrency
- standalone (Standard Severe)
- plus one named scenario
- plus two
- 9. Policy response assumed
- none (pure exposure)
- current plans executed (Standard Severe)
- best practice
- 10. Recovery horizon
- months
- years
- structural (Standard Severe)
Scenario-specific parameters · read-only
| Parameter | Default | Range or options | Note |
|---|---|---|---|
| Cost of firm clean supply relative to new fossil plant | 40 per cent lower | 25 to 55 | Delivered cost of the combined system at the stated reliability, compared with a new gas or coal plant in the same market. |
| Reliability standard met in the trials | 99.9 per cent of hours | 99 to 99.95 | The threshold is defined by cost and reliability together. A discount without the reliability standard does not meet it. |
| Climate zones in which the result is replicated | 5 | 3 to 8 | Sets how many nations can adopt the standard design without local redesign. |
| Time from application to financial close for a standard project | 18 months | 12 to 36 | — |
| Fall in industrial electricity cost in early adopters within five years | 30 per cent | 15 to 45 | Smaller than the generation discount because network charges rise to pay for new transmission. |
| Grid connection lead time in an adopting nation | 3 years | 2 to 7 | The binding constraint under current plans. Above five years, little of the gain arrives inside the test period. |
| Downward revision to expected hydrocarbon demand ten years ahead | 20 per cent | 10 to 35 | Drives the write-down of reserves and the repricing of exporter sovereign debt before volumes fall. |
07Transmission channels
- 1
Independent trials verify that standard combined plants deliver reliable power at 40 per cent below the cost of new fossil plant in several climate zones.
- 2
Lenders treat the design as proven. Standardised projects reach financial close within 18 months and their cost of capital falls.
- 3
Orders exceed the supply of transformers, cable, rigs and critical minerals. Equipment and materials prices rise and delivery times lengthen.
- 4
Grid connection, permitting and power market rules determine which nations turn financed projects into delivered power.
- 5
Industrial electricity costs fall 30 per cent in early adopters. Heat, transport and industry electrify faster and energy-intensive investment relocates.
- 6
Expected long-term demand for oil, gas and coal is revised down. Reserves and fossil plant are written down before volumes fall.
- 7
Hydrocarbon-dependent states face dearer borrowing and lower expected revenue. Public spending, subsidies and currency pegs come under strain.
- 8
Fossil regions lose employment and utilities claim compensation, while importers gain a lasting improvement in their terms of trade.
08Capability loading
High: capability band shifts expected under current plans. Medium: band shifts under 'none' policy response only. Low: strain without band shift. Loads are judgement-based until the Atlas connects. Domains link to the Atlas.
| Domain | Load | Channel |
|---|---|---|
| Hard | ||
| Defence and security | Low | Fuel chokepoints lose some leverage; fiscal strain in exporter states raises instability risk |
| Strategic infrastructure | High | Transmission, storage, interconnection and connection lead times decide who captures the gain |
| Critical technology | High | Manufacture and deployment of modules, cells, drilling systems, reactors and grid equipment |
| Soft | ||
| Government effectiveness | High | Permitting speed, power market reform, revenue diversification and delivery of transition programmes |
| Human capital | Medium | Shortage of electricians, drillers and grid engineers; displaced workers in fossil regions |
| Influence and cohesion | Medium | Exporter leverage declines; regional gains and losses divide opinion within nations |
| Economic | ||
| Macro-financial | High | Exporter budgets, pegs and sovereign spreads; written-down reserves and plant; lower importer fuel bills |
| Industry, trade and supply | High | Energy-intensive industry and data centres relocate to low-cost, connected power |
| Energy and resources | High | Generation mix and price formation change; hydrocarbon demand outlook falls; mineral demand rises |
09Stakeholders
- Government Relevance 3/5
Exposure
Fiscal dependence on hydrocarbons, or the capacity of grids, permitting offices and power market rules to absorb new plant
Actions
- Approve transmission corridors and staff permitting and connection offices ahead of demand
- Reform wholesale power markets so that firm clean capacity is paid for reliability
- Hydrocarbon-dependent states: test the budget against demand 20 per cent lower ten years ahead and bring forward diversification
Watch
- Audited cost and reliability results from combined clean power plants
- Median grid connection lead time and curtailment rates
- Fiscal break-even oil price against the forward price
- Technology Relevance 5/5
Exposure
Power is the main operating input to computing; the siting of data centres and equipment manufacture follows cost and connection time
Actions
- Sign long-term supply contracts in locations with firm clean power and short connection times
- Secure transformers, cable, cells and critical minerals under multi-year agreements
- Design loads for flexible demand so that sites can connect earlier
Watch
- Delivery times for transformers and high-voltage equipment
- Contract prices for round-the-clock clean supply
- Lithium, copper and graphite prices and supply concentration
- Investors Relevance 5/5
Exposure
Hydrocarbon reserves and recently built fossil plant; exporter sovereign debt; relocation of heavy industry; a large pipeline of standardised projects
Actions
- Test holdings against a 20 per cent downward revision to long-term hydrocarbon demand
- Price exporter sovereign debt on fiscal break-even and the size of buffers
- Assess project pipelines by connection date, not by financial close
Watch
- Long-term oil, gas and coal demand outlooks
- Reserve write-downs and cancelled field developments
- Cost of debt for standard clean projects against thermal plant
- Public Relevance 3/5
Exposure
Lower energy bills after a delay; employment lost in coal, oil and gas regions; new lines and plant built near communities
Actions
- Local government: prepare land-use plans and consent procedures for lines and plant
- Training providers: expand courses for electricians, drillers and grid technicians
- Fossil regions: seek transition funding before plants and mines close
Watch
- Retail tariff reviews and network charges
- Closure dates for local plants and mines
- Transition fund commitments and retraining places
10Regional exposure
| Region | Exposure | Rationale |
|---|---|---|
| North America | High | Strong demand from data centres and industry; long connection queues limit the gain; shale and oil sands producers lose asset value |
| Europe | High | Large fuel importer with high industrial power costs; permitting and cross-border transmission decide whether heavy industry stays |
| China | High | Largest maker of modules, cells and grid equipment and largest fuel importer; coal provinces carry the adjustment |
| Indo-Pacific | High | Japan, Korea and Taiwan cut fuel import bills; Australia and Indonesia lose coal and gas revenue but hold minerals |
| South Asia | High | Lower import bills and faster electrification; weak distribution company finances and grid capacity limit delivery |
| Gulf and Middle East | High | Expected hydrocarbon revenue is revised down; strong solar resource and capital allow low-cost producers to diversify |
| Africa | High | Reliable supply becomes affordable where access is lowest; cost of capital constrains delivery; Nigeria, Angola and Algeria lose revenue |
| Latin America and Caribbean | High | Copper and lithium exporters gain and hydropower adds firm supply; Venezuela, Ecuador and Colombia lose oil income |
| Russia and Eurasia | High | Budgets depend on oil and gas; lower expected demand raises borrowing costs and reduces the value of pipeline supply |
11Early-warning indicators
| Indicator | Source | Threshold |
|---|---|---|
| Levelised cost of solar, wind, storage and firm clean power | IRENA Renewable Power Generation Costs; BloombergNEF; Lazard | Firm clean supply at or below 60 per cent of the cost of new gas plant in three or more markets |
| Operating record of enhanced geothermal and advanced fission plants | US Energy Information Administration plant-level generation data; IAEA Power Reactor Information System | Two years of commercial operation at contracted availability |
| Grid connection queue volume and lead time | Lawrence Berkeley National Laboratory, Queued Up; ENTSO-E | Median lead time above five years |
| Clean energy investment and cost of capital by region | IEA World Energy Investment | — |
| Industrial electricity prices by country | Eurostat; IEA Energy Prices | Gap of 30 per cent or more between adopting nations and comparable non-adopters |
| Long-term oil, gas and coal demand outlooks | IEA World Energy Outlook; OPEC World Oil Outlook | Demand ten years ahead revised down by 10 per cent or more between successive editions |
| Fiscal break-even oil price by exporter | IMF Regional Economic Outlook: Middle East and Central Asia | Break-even above the forward price for three consecutive years |
| Critical mineral prices and supply concentration | IEA Global Critical Minerals Outlook; US Geological Survey Mineral Commodity Summaries | — |
12Compounds
- Triggers
- S02 Global funding seizure · If hydrocarbon assets and exporter sovereign debt are repriced abruptly
- S05 Legitimacy rupture · Fiscal retrenchment in hydrocarbon-dependent states
- S01 Trade bloc rupture · Competition for minerals, cells and grid equipment
- S16 Water-efficient food leap · Cheaper power for irrigation, desalination and fertiliser
- S08 AI labour shock · Cheaper firm power lowers the cost of inference at scale.
- Triggered by
- S17 Automated discovery step · Gains in materials, drilling and reactor design
- S13 Great-power détente · Freer trade in modules, cells and grid equipment
- S03 Regional war spillover · A fuel price shock accelerates the move away from imported hydrocarbons
- S11 Debt service reset · Restored creditworthiness lowers the cost of capital for power projects in participating states
- S12 Market access opening · New industrial load and lower tariffs on equipment bring standardised clean power projects forward
- Amplified by
- S11 Debt service reset · Fiscal room for grid investment in indebted states
- S12 Market access opening · Common standards and lower tariffs on equipment
- Amplifying trends
- Enhanced geothermalSolar manufacturing cost declineBatteries & energy storageGrid expansion & demand flexibilityHydrocarbon revenue dependenceAdvanced nuclear fissionElectrification of heat & industryCritical minerals supply constraints
- Key trends
- Batteries & energy storageVery highCommodity dependence & price volatilityVery highSolar manufacturing cost declineVery highRenewable generation expansionVery highGrid expansion & demand flexibilityVery highEnergy import dependenceVery highHydrocarbon revenue dependenceVery highAdvanced nuclear fissionVery high
From GINC Trends: the trends rated Very high or Critical for this scenario, of 250. All S15 trend scores.
13Rating rationale
| Rating | Band or level | Why |
|---|---|---|
| Likelihood, two years | 3Possible | Each component is commercial or close to it: battery project costs reached a record low in 2025 and the first commercial enhanced geothermal phase is due on the grid in 2026. The Standard Severe event needs more: independent verification of the combined system at a 40 per cent discount to new fossil plant in several climate zones. Trial periods and construction lead times make that possible within two years but not probable. |
| Likelihood, ten years | 4Likely | Solar electricity costs fell by more than 80 per cent in a decade and storage costs are following. Ten years allows several firm clean options to complete commercial trials and reach standard designs. The band is not 5 because the threshold requires reliability and replication across climate zones, and firm clean generation has a much shorter cost record than solar or batteries. |
| Systemic impact | 4Major | Electricity is an input to every sector. A 30 per cent fall in industrial power costs in adopting economies, faster electrification and the relocation of energy-intensive investment change output in many nations, while hydrocarbon asset values and exporter revenues are revised down. GINC places the combined change, counting gains and losses, at 2.5 to 5 per cent of global output over five years. Grid constraints keep it below level 5. |
| National impact | 4Major | The highest dimension reached is economic. A hydrocarbon-dependent state faces lower expected revenue, dearer borrowing and written-down reserves; a grid-ready importer gains a lasting cost advantage. Level 4, not 5, because prices and volumes fall over years after expectations move, which leaves time to adjust. The 1986 oil price collapse shows the level reached when the revenue loss is abrupt. |
| Confidence | medium | Component cost trends are well measured. The cost of the combined firm system, the pace of standardised finance and the response of hydrocarbon demand are less certain. |
Source of scores: model-panel-v0.5. Confidence refers to the rating, not the scenario. Calibration sources are listed with the anchors above and on the scenario methodology page.
14Open questions
Contested assumptions for the panel to resolve.
- Whether a 40 per cent discount to new fossil plant is the right threshold, or whether the test should be the running cost of existing plant, which is a harder standard.
- Whether an event that takes five years to change costs and revenues is a shock with an onset of months or an accelerated trend with a dated announcement.
- How to rate one scenario in which the typical highly exposed nation may be a grid-ready importer that gains or a hydrocarbon-dependent state that loses.
- Whether the gain is material for a nation whose connection lead time exceeds the five-year test period.
15Commentary
No signed commentary in this build.
16Version and citation
- Version
0.5.0· active ·clean-power-threshold- Change log
0.5.0· 9 October 2026 · Rebuilt in the second pass from Energy abundance breakthrough: open-ended abundance replaced by an observable threshold, firm clean power at 40 per cent below new fossil plant; onset moved from years to months; systemic impact raised to 4 and national impact lowered to 4; fusion and a fixed oil price fall removed.
Rating history
One row per edition. Each edition page is frozen at release; corrections are published as errata.
| Edition | Rank | L2y | L10y | Systemic | National | Confidence | Edition view |
|---|---|---|---|---|---|---|---|
| 2027 | Not ranked | 3Possible | 4Likely | 4Major | 4Major | medium | Open |
Versions
| Version | Date | Change |
|---|---|---|
| 0.5.0 | 9 October 2026 | Rebuilt in the second pass from Energy abundance breakthrough: open-ended abundance replaced by an observable threshold, firm clean power at 40 per cent below new fossil plant; onset moved from years to months; systemic impact raised to 4 and national impact lowered to 4; fusion and a fixed oil price fall removed. |
Citation and downloads
Cite as
GINC (2027). Scenario S15 Cheap firm clean power becomes available at scale, Scenario Library v0.5. scenarios.ginc.org/scenarios/clean-power-threshold
Content and data are published under CC BY 4.0.